Bridge Repair Work Beginning March 24

The Maine DOT will be performing bridge repair work on the Winter Street and Oak Street train overpasses.

Weather permitting, the work schedule is as follows:

3/24, 3/25 - Winter Street

3/26, 3/29 - Oak Street

Through traffic will be detoured around these work sites during the day, but residents will have access to their driveways at all times.  Through traffic will be restored each evening.

Any questions regarding these repairs may be directed to Don McKenna of the Maine DOT at 207-462-4474.