June 13, 2017

Construction update (June 13, 2017)

In the last week:

  • Sargent has removed the existing topsoil, clay, and sand cover system from the phase 3 area
  • The topsoil and clay were moved to public works for temporary storage
  • The sand which has some waste mixed in, was moved to the active disposal area for permanent burial
  • The existing leachate surge pond has been mostly deconstructed; a temporary pond has been constructed and is in operation
  • Placement of gas collection lines has begun
     

In the next week:

  • Gas collection pipe installation will continue
  • The finished grading of the subgrade will be completed
  • Geogrid will be installed on the subgrade
     
    Existing Cover Removal Existing Cover Removal Existing Cover Removal Existing Cover Removal
    Existing Cover Removal Gas Pipe Installation Leachate Pond Deconstruction Leachate Pond Deconstruction