July 18, 2017

Continued installation of gas collection piping

Installed 9-inch thick impervious borrow

Constructed northern and eastern berms to secondary liner grade

Begun fusing pipe segments together for leachate collection system

Began deploying secondary liner, including air testing

Removed existing leak detection manholes

Trucking will be increasing for the next couple of weeks as sand and clay are hauled in from Durham.  This will include Saturday trucking for at least the next couple.